|




|
 |
Energy
|
Air Quality Services
 |
We developed and negotiated an Air-Permit application for a new 65 million gallon per year ethanol plant in Ohio. This permit was challanged by a group that didn't want to see the plant built by the proposed construction manager. The application successfully withstood the challange.
|
 |
We developed and negotiated an Air-Permit
application for a new, clean 500-megawatt
power plant for prevention of significant
deterioration and non-attainment review. After
significant review and comment by both the
Michigan Department of Environmental Quality
and the US Environmental Protection Agency,
the permit was issued. Unfortunately, partly
because of the added expense dictated by the
agencies to control oxides of nitrogen (an
attainment pollutant) to a process that is
magnitudes cleaner than its competitors, construction
has not yet started on this facility.
|
 |
We performed a strategic review for developing
60-megawatt combined-cycle power plant on
West Side of Michigan in terms of air quality
permitting issues. We reviewed two siting
options and outlined permitting issues. There
were significant regulatory differences between
the sites and our review was used to help
determine the most cost-effective site. One
site would have required a Federal New Source
Review air permit and the other site could
have been permitted through the state permitting
system without the special federal add-on
equipment requirements.
|
 |
As part of a competitive bidding process,
we assisted a major gas development company
by performing a dispersion modeling study
to determine maximum ambient impacts and appropriate
stack heights for a carbon dioxide removal
plant with reciprocating engines. Through
this process, the company had a much better
understanding of the potential risks that
they would encounter through the air permitting
process.
|
 |
We developed a synthetic-minor air-permit
application and negotiated the permit for
reciprocating engines to serve a natural gas
storage system. We developed an innovative
procedure to monitor continuous compliance
based on a pre-approved stack testing protocol,
thereby saving the customer from the uncertainty
associated with a Best Available Control Technology
review for the compressor station.
|
 |
We prepared a synthetic-minor air-permit application
for gas turbine addition at a natural gas
compression station. In this case, the synthetic
minor status saved the company from the uncertainties
of performing dispersion modeling on existing
nearby sources. This permit was issued within
3 weeks of application submittal.
|
Environmental Management
Systems
 |
Remote facilities pose challenges for environmental
management. We developed and performed multi-media
"mock inspections" for a number
of utility field stations. In addition to
testing the level of robustness of the environmental-management
system at the stations, this work resulted
in a much better understanding by the station
operators of the environmental aspects of
their operation. This program was designed
to minimize fear and maximize learning. Each
participant was able to use the system to
successfully deal with an inspector. Each
participant saw the process as valuable to
his or her understanding of the issues.
|
 |
Fast access to environmental information is
critical for large and small operations. We
worked with a software company for corporate
wide installation of material safety data
sheets and SARA right to know modules for
a gas transmission company.
|
Environmental Services
 |
When a chronic oil leak threatened the property
at a compressor station, we managed the investigation
and remediation and then prepared the Closure
Report for this voluntary remediation.
|
 |
We prepared FERC Air and Noise reports for
a number of complex projects. We have also
developed data for facilities to present to
the public concerning the noise impact from
their operations. Our public relations and
community consensus building skills added
value.
|
 |
We developed a successful strategy to mitigate
community-noise impacts due to directional
drilling. This project was to construct a
new pipeline across a major river that is
also an international border. Single-family
residences, condominiums and medical offices
were directly adjacent to the site. After
measuring background ambient-noise levels,
we developed an innovative system of partial
enclosures, barriers and attenuation equipment
to keep noise impacts below guidelines. During
the construction process, we monitored the
noise, and fine-tuned the mitigation to minimize
noise impacts at the sensitive receptors.
|
 |
We
prepared a checklist-based process to perform
the required weekly environmental inspection services
for construction at a natural gas compressor station.
We also developed a training procedure that the
construction manager implements at the site. The
process we use provides additional detail than
required by the FERC inspection process and we
take the responsibility to perform the inspections
each and every week during the construction, thereby
outsourcing this process and leaving the Company’s
people to manage other important tasks.
|
|
|
| |